Quality/Plans/Handset UX ramp-up 1.1
Ramp-Up for MeeGo 1.1 HandSet UX QA
- Test Execution
- Acceptance Testing - OK
- Sanity Testing - OK
- Basic Feature Testing - OK
- Extended Feature Testing - 15th October (Done already for Aava)
- System Functional Testing - 15th October
- System Non-Functional Testing (Response Time) - 15th October
- Test Asset Storage (in TestLink)
- Sanity Test Set - OK
- Basic Feature Testing - OK
- Extended Feature Testing - OK
- System Functional Testing - ONGOING, 19th September
- System Non-Functional Testing (Response Time) - 7th October
- Component Test Plans
- Component Test Plans available - OK
- Testability of Features
- Note! Pre-condition is that Testability selection is implemented to Featurezilla - OK
- QA owners to set Feature testability status to Bugzilla and identify final gap - OK
- List of NOK items pointed to Product Management - OK
- Only open area is Photo viewer, that needs improvements.
- Main Risks / Issues
- Automation solution needed to freed capacity