(→1.2 Release) |
m (→1.1 Release) |
||
| (2 intermediate revisions not shown) | |||
| Line 1: | Line 1: | ||
== 1.1 Release == | == 1.1 Release == | ||
| - | [http:// | + | [http://qa-reports.meego.com/1.1 Test Results] |
| - | === N900 | + | === N900 Summary === |
| - | + | ||
| - | + | ||
* Pass rate of total went up from 39% (0921) to 52% (0927) | * Pass rate of total went up from 39% (0921) to 52% (0927) | ||
| Line 15: | Line 13: | ||
* Video Play works. | * Video Play works. | ||
| - | === Aava | + | === Aava Summary === |
| - | + | ||
| - | + | ||
* Pass rate of total went from 61% (0921) to 67% (0926). | * Pass rate of total went from 61% (0921) to 67% (0926). | ||
| Line 66: | Line 62: | ||
| 22 September | | 22 September | ||
| 1 October | | 1 October | ||
| - | | [ | + | | [[Quality/TestPlan/MeeGo Core Test Plan|The Core OS Program test plan]] is under review. |
|- | |- | ||
| Architecture Defined | | Architecture Defined | ||
Contents |
| Check Item | Owner | Planned | Actual | Comment |
|---|---|---|---|---|
| Requirements Filed | Gavin Hindman | 10 September | 30 September | All the 1.2 requirements must be selected. The "unspecified" and "1.2" requirements. |
| Requirements Testability Check Completed | Tommi Toropainen | 30 September | 15 October | Not-studied features can be found from here. Takes 1-2 weeks after the "Requirements Filed". |
| 90% Requirements Testable | Gavin Hindman | 30 September | 22 October | Not-testable features can be found from here. Workshop required to close this case. |
| TMS assigned | Alexander Kanevekiy | 30 September | 29 October | Features that are missing the TMS can be viewed here. |
| Test Plan Approved | Tommi Toropainen | 22 September | 1 October | The Core OS Program test plan is under review. |
| Architecture Defined | Sakari Poussa | 30 September | 30 September |