Basic Feature Testing - 3rd September. ONGOING, 1st execution results should be available soon.
Extended Feature Testing - 17th September
System Functional Testing - 17th September
System Non-Fucntional Testing (Response Time) - OK (part of Sanity Testing reports)
Test Asset Storage (in TestLink)
Sanity Test Set - OK
Basic Feature Testing - OK
Extended Feature Testing - 17th September
System Functional Testing - 17th September
System Non-Fucntional Testing (Response Time) - OK (part of Sanity Testing reports)
Component Test Plans
Component Test Plans available - 17th September
Testability of Features
Note! Pre-condition is that Testability selection is implemented to Featurezilla - OK
QA owners to set Feature testability status to Bugzilla and identify final gap - OK
List of NOK items pointed to Product Management - 8th September
Testability improvements in place - 13th September
Main Risks / Issues
Visibility to Features that are moved from MeeGo 1.1 release to MeeGo 1.2 release. MeeGo 1.1 HandSet UX test sets must be 'cleaned' based on this visibility.
No public N900 weekly SW image, might be that QA must use internal releases for N900
Settings testing area lacking of test cases - risk of inadequate test coverage