MCTS Test Automation - Workshop on Tuesday November 30th 2010

Targets

  • Agree the architecture for the system
  • Plan the proof-of-concept for the system

Test Automation Phases

Divided into phases based on MCTS test automation priorities.

Phase 1:
External Device Verification
Target: Provide support to attach external devices into test automation environment and control within test runs.
Phase 2:
Peer DUT Verification
Target: Provide support to attach multiple DUTs into test automation environment and interaction between DUTs.

External Device Verification

Design Option 1

Control of the devices is modelled on test plan level. Test plan XML defines, for which device the command is targeted to.

Components ext verification option1.png

  • Rework is needed for the current test asset.
  • Execution of test asset depends on testrunner-lite and test plan XML. Is it needed to execute test binaries standalone?
  • Test case doesn't have the ability to control the devices. Is it a problem?

Design Option 2

Test plan XML doesn't take account to the environment. Test binaries have the control to the external devices.

Components ext verification option2.png

  • Some modification needed in test asset
  • More work needed on test tools side
  • Test case can control external devices
  • Execution doesn't depend neither on test plan XML nor testrunner-lite
  • Control of the system is both on host and target side

Design Option 3

Combination of Option 1 and Option 2 or something else?

General Concerns

  • Test automation environment relies on IP over USB and SSH connection. How to handle USB test cases?
  • Where to check capabilities of the system before test run?